Florida Statute 713.23 – Payment Bond Guide

Florida Statute 713.23 – Payment Bond Guide (Contractors & Surety)

What 713.23 Covers

Section 713.23 of the Florida Statutes governs payment bonds on bonded construction projects, and how those bonds interact with lienor rights and required notices. The high‑level sequence is simple: record the Notice of Commencement with the bond, serve early notice if you’re not in privity, serve a sworn Notice of Nonpayment if unpaid, and file suit on time.

Record before work starts

Owner/GC

The Notice of Commencement (NOC) should be recorded before commencement and include a copy of the payment bond to exempt the owner. The bond must be at least the original contract amount and issued by an authorized surety.

Early notice preserves rights

Lienors not in privity (subs/suppliers)

Serve a Notice to Contractor (can be combined with a Notice to Owner) within 45 days of first furnishing to look to the bond for payment. If the bond wasn’t recorded before start, you may serve within 45 days after receiving a copy of the bond.

If unpaid, act fast

Lienors

Serve a sworn Notice of Nonpayment on the contractor and a copy to the surety no later than 90 days after last furnishing. If still unpaid, sue the contractor or surety within 1 year of last furnishing (or 60 days after a Notice of Contest is served).

Practical tip: Calendar three dates the day you start furnishing — the 45‑day notice window, the 90‑day nonpayment window, and the 1‑year suit deadline. Certificates of occupancy or substantial completion do not change these clocks.

Step‑by‑Step Flowchart (Decision Tree)

Follow this sequence to preserve and enforce rights under a 713.23 payment bond.

Jump to statutory forms

Timelines & Triggers (At a Glance)

Bonded Project Timeline

Clocks run from your actual last furnishing of labor/materials; not from CO or substantial completion.

Before Start
NOC + Bond
Day 1–45
Notice to Contractor
By Day 90
Notice of Nonpayment
By 1 Year
Suit on Bond

Contest Shortens Deadline

If the contractor/attorney records and serves a Notice of Contest of Claim Against Payment Bond, your time to sue is shortened to 60 days from the date of service.

Keep your service address current on your notices to ensure you receive a contest notice.

Who Does What

Owner / Contractor (GC)

  • Record NOC with the payment bond attached before commencement.
  • Furnish a true copy of the bond to any lienor who demands it (cost of reproduction).
  • Contractor/attorney may record and serve a Notice of Contest after a lienor’s nonpayment notice.

Subcontractors & Suppliers (Lienors not in privity)

  • Serve Notice to Contractor within 45 days of first furnishing (or within 45 days of receiving the bond if the bond wasn’t recorded before start).
  • If unpaid, serve a sworn Notice of Nonpayment within 90 days of last furnishing; copy the surety.
  • File suit on the bond within 1 year of last furnishing (or within 60 days if contested).

Surety

  • Bond must be issued by an authorized surety; protects lienors supplying labor, services, or materials.
  • Surety is not discharged by contractor–owner contract modifications (liability capped at penal sum).
  • No advance waiver by lienors of the right to sue on the bond.

Required Notices & Recordings

Record

  • Notice of Commencement with Payment Bond attached (county where the property lies).
  • Notice of Bond (to transfer a recorded claim of lien to the bond), then serve it with a copy of the bond to the lienor and record proof of service.

Serve

  • Notice to Contractor (for lienors not in privity) within 45 days of first furnishing.
  • Notice of Nonpayment, under oath, within 90 days of last furnishing; serve on GC and copy the surety.
  • Notice of Contest of Claim Against Payment Bond (GC/attorney) to shorten suit time to 60 days.

Statutory Forms (Copy‑Ready)

These are the statute’s “substantially the following form” templates. Fill in project‑specific details. Consider having forms reviewed by counsel.

Notice to Contractor (may be combined with Notice to Owner)
Notice of Nonpayment (sworn)
Notice of Contest of Claim Against Payment Bond (contractor/attorney)
Notice of Bond (to transfer a recorded lien to the bond)
Payment Bond (statutory form)

Quick FAQs

Does retainage require a nonpayment notice?

No. Failure to receive retainage of ≤10% of the value furnished is not considered a nonpayment requiring the 90‑day notice. Still, include retainage amounts when you do serve the notice.

What is “last furnishing”?

It’s the last day you actually furnished labor, services, or materials (or for rental equipment, the last day equipment was on site and available). CO or substantial completion are not the measuring events.

Can a bond restrict who is protected or change the deadlines?

No. A payment bond may not narrow protected classes, change venue, shorten/extend duration, or add extra conditions beyond the statute; such clauses are unenforceable.

What if there’s a mistake in my Notice of Nonpayment?

Non‑prejudicial negligent mistakes don’t defeat a valid claim. But a fraudulent notice (willful exaggeration or gross negligence) forfeits bond rights.

Primary Sources

© Florida Surety Bonds • Educational content only • All trademarks belong to their respective owners
Discussing Surety Bonds at Construction Site

Get started with your Surety Bond.

For start-ups, design-build, small and large contractors, all we do is bonding. Let us know how we can help you.